Facilities
facilities
Jump over the site's masthead's navigation bar.
Facilities Planning

Design Guidelines

This guide is intended to provide an overview and to serve as a guide to architects, engineers and other consultants providing professional services for all new construction, remodeling, rehabilitation and maintenance projects at Illinois State University.

Objectives

The design and construction of all projects for the Illinois State University will normally be guided by the following objectives:

  1. Fulfilling the needs of the user department.
  2. Design excellence and maintainability.
  3. Compliance with University Campus Planning Policies.
  4. Economic balance, commensurate with available funds and design objectives, between initial construction cost, building permanence and operation-maintenance costs.
  5. Compliance with applicable Codes, including those pertaining to the handicapped and the requirements of participating government agencies.

Cover page and Table of Contents-3-11

Specifications

Facility Construction Subgroup

Facility Services Subgroup

Site Infrastructure Subgroup

Process Equipment Subgroup

  • Division 40 – Process Integration
  • Division 41 – Material Processing and Handling Equipment
  • Division 42 – Process Heating, Cooling, and Drying Equipment
  • Division 43 – Process Gas and Liquid Handling, Purification, and Storage Equipment
  • Division 44 – Pollution Control Equipment
  • Division 45 – Industry-Specific Manufacturing Equipment
  • Division 46 – Reserved
  • Division 47 – Reserved
  • Division 48 – Electrical Power Generation
  • Division 49 - Reserved

Complete Appendix _9-6-11

Entire Design Guidelines_9-26-11

 

Illinois State University

© 2012 Illinois State UniversityAn equal opportunity/affirmative action university encouraging diversity.Privacy StatementIdentity StandardsAppropriate Use Policy