Watterson Commons - Emergency Generator

Architects/Engineers: Farnsworth Group
General/Contractor: JohnCo
ISU Administrator Contact: Rick Kentzler
ISU Project Manager: Mike Johnson
Project Status: Construction
Fund Source: Bond Proceeds and Reserves
Project Budget: 1.98 million

Description

This $0.75 million project was approved by the Board of Trustees in July 31, 2009. The Board of Trustees approved a $1.23 million increase to add all of Watterson Commons Dining Center and the requirement for additional items in Watterson Towers to the project budget on February 19, 2010, bringing the total to $1.98 million. The project involves replacement of the emergency generator serving Watterson Towers and Watterson Commons including full back-up power for Watterson Commons. It is anticipated to be completed in December of 2011.

Construction updates (January 28, 2013)

Farnsworth was the designer for a new emergency generator and enclosure project. The contractor, Anderson Electric, has completed the installation of the new emergency generator as well as the electrical connections to the generator. The designer is currently beginning project close out such as-built drawings and setting up a schedule for the remaining test during spring break.
The construction documents for the generator enclosure were completed and forwarding to Purchasing for review.

Construction updates (October 8, 2012)

Farnsworth consultant is working on the close out documents.

The Watterson Generator enclosure documents were completed and they are in review at Purchasing.

Construction updates (September 24, 2012)

Generator has been installed .The contractor, Anderson Electric, has completed the electrical connections to the new generator. The work has been completed. The Watterson generator enclosure documents are in review at Purchasing.

Construction updates (June 18, 2012)

View project location (PDF).

The footings and foundation wall for the new generator have been completed as well as the exterior trenching and conduit installation. The trenches have been backfilled. A new electric manhole has been set. The basket ball and volley-ball courts were opened for student use.

The generator arrived on site on Saturday, September 17, 2011 at 8:00 a.m. A crane was used to unload the generator and set to the enclosure successfully within a short period of time. The south/east parking lots were reopened immediately following that work. Generator has been installed.

The contractor, Anderson Electric, has completed the electrical connections to the new generator. They continue to work on minor work and clean-up to finish up the project.

The Watterson generator enclosure documents are in review at Purchasing.

Click image for large version.

Photo A: A crane was used to unload the generator

Watterson Emergency Generator - A crane was used to upload

Photo B: The generator was set to the enclosure

Emergency generator was set to the enclosure

For other projects information, please visit Campus Construction Updates.