Milner Library Pedestrian Ramp Repair (150075)
Project Start and Completion Dates
- Start Date: Fall 2018
- Completion Date: 11/30/18
Type of Work
Concrete ramp repairs
Location of Work
Exterior ramp along south side of Milner Library
Staging Area
Southeast corner of Milner Library and ramp
Periodic Noise/Odors/Interruptions
-
Sawing, hammer drilling, material movement, skid steers, etc.
Possible odor from waterproofing.
Periodic ramp closures.
Accessibility, Health, and Safety Notes
-
Ramp closures
Do not cross construction barriers or enter construction area.
ISU Project Manager
Tony Herter
Phone: (309) 438-1927