Watterson Dining Commons Expansion (140286)
Project Start and Completion Dates
- Start Date: 5/1/2018
- Completion Date: 5/17/2019
Type of Work
New building and remodeling. All trades.
Location of Work
New Addition to the East side of Watterson Dining Commons.
Staging Area
South Side of the Building (Basketball Court)
Periodic Noise/Odors/Interruptions
- General construction noises.
Accessibility, Health, and Safety Notes
- Cranes and general construction concerns.
- Sidewalk closed on the East side of the building.
- New construction fence layout starting May 13, 2019
ISU Project Manager
Brian Emme
Phone: (309) 438-8605
Notes
This project has a lot of construction activity. Be aware of construction activity around this building.